Construction Tender Technical Proposal: What to Include
11 November 2026 · 7 min read · By NextBid Bid Experts
What a construction tender technical proposal contains: method statements, site organisation, equipment, manpower, schedule, quality and HSE plans, and subcontractors.
A construction tender technical proposal (العرض الفني) shows the evaluation committee how you will build the works: a method statement for each major activity, the site setup, the equipment and people you commit, a schedule that ties them together, and your quality and safety arrangements. The tender booklet (كراسة الشروط والمواصفات) sets the sections, their order and the scoring criteria, so use this guide to decide what to prepare and the booklet to decide how to present it.
For the general structure of any technical offer, read how to structure a technical proposal that scores; for the schedule, see the work plan and schedule guide.
How is a construction technical offer evaluated?
The booklet sets the criteria, their weights, the essential pass or fail conditions and the minimum technical score; the committee applies what the booklet states. There is no national pass mark. For construction, the current evaluation-criteria controls (2021) set mandatory weight ranges for the technical and financial criteria: 10% to 30% technical and 70% to 90% financial at or above the high-value level, and 5% to 20% technical and 80% to 95% financial below it. Those ranges come from the controls, not from the law.
Price carries a large weight in construction, but the technical offer is still the gate. Where two files are used, the committee examines the technical offers first, excludes the unacceptable ones and returns their financial offers unopened. The Implementing Regulations make two files mandatory from SAR 5 million, and below that the entity chooses. A bidder that misses the minimum technical score is out before its price is read. See the two-envelope system on Etimad.
How do you write a method statement for each major activity?
Take the activity headings from the bill of quantities and the specifications, so the committee can match each statement to the work it is scoring. Write one method statement per major activity or work package, not one per line item, unless the booklet asks for more. Each statement can follow the same short pattern:
- Scope: what the activity covers and where it starts and ends, using the booklet's own terms.
- Sequence: the steps in the order you will carry them out, and what must be finished before the next activity can start.
- Resources: the crew, equipment and materials the activity uses, matching the equipment list and the manpower histogram.
- Interfaces and constraints: other trades, existing services, access, and any restriction the booklet or the site imposes.
- Quality and safety: the inspection and test points and the main hazards with their controls, so the activity is covered in the plans described below.
Describe how you will do the work on this site, not how the work is done in general.
What goes into site organisation and temporary facilities?
Draw this section against the site described in the booklet, and if the booklet provides for a site visit, use what you saw. Cover:
- Site layout: access and egress, storage and laydown areas, offices and worker welfare facilities.
- Temporary utilities and services: power, water and communications during construction.
- Material and equipment movement: delivery routes, lifting and traffic arrangements.
- Site security and the protection of existing structures, services and neighbouring operations, with waste handling.
How do you present equipment, manpower and the schedule?
These three parts must agree with each other and with the method statements: a crane in the equipment list with no lift in any method statement invites doubt.
| Part | What to show | How to keep it consistent |
|---|---|---|
| Equipment list | Type, quantity and capacity of each major item, whether it is owned or leased, and the ownership or lease evidence in the form the booklet asks for. | Every item appears in at least one method statement, and its use fits the schedule. |
| Manpower histogram | Headcount by trade over the contract period, with the supervisors and key personnel named in the offer. | Peaks and troughs follow the schedule; the key personnel match the CVs you submit. |
| Schedule | Activities, durations, logic links and milestones within the contract period the booklet sets. | Durations reflect the crews and equipment you listed, not a target date worked backwards. |
What do the quality and HSE summaries need, and where does the Saudi Building Code fit?
Keep the quality plan and the health and safety (HSE) plan tied to the works. For quality, show the inspection and test points, material approvals and handover steps. For HSE, show the main hazards of each activity, the controls, supervision and emergency arrangements. Use the standards that the booklet and the specifications name, and if they ask for a particular plan or form, supply that.
The Saudi Building Code Application Law (Royal Decree M/43, 2017) provides that the code applies to construction work in both the public and private sectors, and the phases and dates of mandatory application are set in its Implementing Regulations. Refer to the parts of the code that the specifications invoke, and if the booklet and the code appear to differ, raise it in the inquiry period.
How do you present subcontractors and classification?
Where the tender requires a contractor classification, the entity cannot accept an offer from an unclassified contractor under the Contractor Classification Law, and your certificate must be valid at opening. See contractor classification for the certificate itself.
Subcontracting is where the law is changing. Under the current law, subcontracting needs the entity's written approval and the contractor stays jointly liable for the subcontractor's work. The current Implementing Regulations cap the subcontracted works at 30% of the contract value, with a share between 30% and 50% allowed only with prior consent and more than one subcontractor. The new law, which takes effect in early January 2027, keeps the written approval and the joint liability and leaves the cap to its Implementing Regulations, so check the tender booklet for the limit that applies. A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it, so check that tender's booklet and announcements.
In the subcontractor list, name only the packages you intend to subcontract, say what each package covers, and show the subcontractor's relevant classification and experience where the booklet asks for it. Keep the total within the limit the booklet sets.
Build the construction technical offer around the bill of quantities and the schedule: every method statement, resource and subcontract package should trace back to a line the committee can find and score, in the order the booklet sets.
Frequently asked questions
Do I need a method statement for every item in the bill of quantities?
No, unless the booklet asks for it. Write one for each major activity or work package, and make sure the headings match the bill of quantities so the committee can map them.
Can I list leased equipment in my equipment list?
Show each item as owned or leased and attach the evidence in the form the booklet asks for. If the booklet limits leased equipment or asks for specific ownership documents, follow it.
How much of a construction contract can I subcontract?
Under the current Implementing Regulations the cap is 30% of the contract value, with a share between 30% and 50% only with prior consent and more than one subcontractor. The new law, which takes effect in early January 2027, leaves the cap to its Implementing Regulations, so check the booklet. A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it.
Does the Saudi Building Code apply to my tender?
The Saudi Building Code Application Law says the code applies to construction work in the public and private sectors, and its Implementing Regulations set the phases and dates of mandatory application. Cite the parts that the specifications invoke and use the inquiry period if anything is unclear.
Our bid management team writes technical and commercial proposals for construction tenders, written natively in Arabic and English, working from your booklet, your records and your site information, and you review and approve what is submitted.