Advance Payment Guarantee: How Government Advances Work
19 November 2026 · 5 min read · By NextBid Bid Experts
An advance payment guarantee backs a government advance. The current law caps advances at 10%; the new law, which takes effect in early January 2027, widens what an entity may pay.
An advance payment guarantee (ضمان الدفعة المقدمة) is a bank guarantee, equal in value to the advance, that a contractor gives a government entity before receiving an advance on a contract. Under the current Government Tenders and Procurement Law and its Implementing Regulations, an entity may pay an advance of up to 10% of the total contract value, and only against that guarantee. The new law, which takes effect in early January 2027, opens the door to larger advances.
What is an advance payment guarantee?
An advance is money the entity pays the contractor before the work is invoiced, so the contractor can fund the start of the contract. The guarantee protects the entity's money until the advance has been recovered. It is a different instrument from the initial guarantee given with the offer and the final guarantee of 5% of the contract value given after award, which our guide to bid bonds and performance guarantees covers.
What does the current law allow?
The current law says an entity may pay the contractor an advance in return for a bank guarantee of equal value, as the Implementing Regulations specify. The Implementing Regulations set the conditions:
- The advance is optional: the entity "may" pay it, so the contractor has no automatic right to one.
- It cannot exceed 10% of the total contract value.
- It is paid only after the contractor provides an advance payment guarantee equal to the advance.
- It may be split into more than one payment.
- No advance is paid when a contract is extended or additional works are assigned.
On an illustrative contract of SAR 2,000,000, the 10% ceiling is SAR 200,000. Whether an advance is offered at all, and on what terms, is something to confirm in the tender booklet (كراسة الشروط والمواصفات) and the draft contract before you price.
How is the advance recovered?
Under the current Implementing Regulations the entity recovers the advance by deductions from the contractor's invoices, starting with the first invoice. As the advance is recovered, the guarantee is reduced to match. An advance is therefore a change in timing, not extra revenue: it puts cash in your hands early and takes it back from later payments. If the contract is priced as lump sum or unit price, the deductions work against the same contract value either way, so model them in your cash-flow plan.
What changes under the new law?
Under the current law, the Implementing Regulations cap an advance at 10%. The new law, which takes effect in early January 2027, lets the entity pay a part of the contract value, or the whole value, in advance against an equal bank guarantee, as the new Implementing Regulations clarify. It also allows those Regulations to list cases exempt from the bank guarantee. A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it, so check that tender's booklet and announcements.
| Point | Current law and Regulations | New law (takes effect in early January 2027) |
|---|---|---|
| Advance amount | Up to 10% of the total contract value (Regulations) | A part of the contract value, or the whole value; the limit is left to the new Implementing Regulations |
| Guarantee | Bank guarantee equal to the advance | Equal bank guarantee; the Regulations may list exempt cases |
| Recovery | Deducted from each invoice, starting with the first (Regulations) | Not confirmed until the new Implementing Regulations are issued; check the tender booklet |
How do you request an advance and plan around it?
- Read the booklet and draft contract to see whether an advance is offered, its amount and its conditions.
- Ask your bank for a guarantee equal to the advance, in the form the entity requires.
- Follow the request procedure the booklet or contract sets, and do not rely on a format of your own.
- Build the deductions into your cash-flow forecast so the advance does not look like margin.
- If the bank charges for issuing the guarantee, count that charge in your cost build-up, as in our guide to preparing the financial offer.
An advance helps cash flow, not profit. Under the current law it is capped at 10% and needs an equal bank guarantee; the new law, which takes effect in early January 2027, widens what an entity may pay, with limits left to its Implementing Regulations, so read the booklet before you price.
Frequently asked questions
Is an advance payment guaranteed on a government contract?
No. Under the current law the entity may pay an advance, so it is not a right, and the booklet and contract state whether one is offered. The new law, which takes effect in early January 2027, keeps the same permissive wording.
What is the maximum advance payment under the current law?
The current Implementing Regulations cap it at 10% of the total contract value. The new law, which takes effect in early January 2027, leaves the limit to its new Implementing Regulations, so check the tender booklet.
Do I need a bank guarantee to receive an advance?
Yes under the current law: the advance is paid against a bank guarantee equal to its value. The new law, which takes effect in early January 2027, keeps that requirement but allows its Implementing Regulations to list exempt cases.
How is the advance paid back?
Under the current Implementing Regulations it is deducted from the invoices, starting with the first, and the guarantee is reduced as it is recovered. For the new law, which takes effect in early January 2027, the recovery method is not confirmed until its Implementing Regulations are issued, so check the tender booklet.
Our team's pricing analysis covers cost analysis and market benchmarks, and the client always approves the final prices. If a contract offers an advance, it helps to set the cash-flow assumptions behind the price early. Read how this fits the wider offer in the difference between technical and financial proposals.