Lump Sum vs Unit Price Contracts in Saudi Tenders

13 November 2026 · 6 min read · By NextBid Bid Experts

A lump sum pays one fixed price for a defined scope; a unit price contract pays tender rates on measured quantities. Here is how each is priced and how to spot which one a booklet uses.


A lump sum contract pays the contractor one fixed price for a defined scope of work. A unit price contract pays a rate for each unit of work, multiplied by the quantity actually measured. The difference decides who carries the risk when real quantities differ from the estimate, so it should change how you price before you open the bill of quantities.

This guide explains how re-measurement works, how risk is shared and how to tell which basis a tender uses. The tender booklet (كراسة الشروط والمواصفات) and its draft contract state the pricing basis; the legal rules quoted come from the Government Tenders and Procurement Law and its Implementing Regulations.

What is a lump sum contract?

The bidder offers one total price for a defined scope. The price does not move with the booklet's quantities while the scope stays the same. If the real quantity turns out higher than you assumed, you absorb the difference unless the scope itself was changed by a formal change order.

What is a unit price contract, and what is re-measurement?

The bill of quantities (BOQ, جدول الكميات) lists each item with an estimated quantity, and the bidder prices a rate per unit. The offer total is the sum of rate times estimated quantity, but the payment follows the work as measured. Re-measurement means the executed work is measured and paid at your tender rates, so the contract value can move up or down with the quantities.

How do the two compare?

PointLump sumUnit price
What you priceOne total for the defined scopeA rate for every BOQ item
What you are paidThe agreed total, on the payment termsRates times measured quantities
Quantity riskWith you, within the defined scopeWith the entity, within the BOQ items
Where it hurtsA take-off that is too low or an assumption that is missingA rate that does not cover its full cost
Scope changesPriced through a change orderPriced through a change order

How should you price each one?

  • Lump sum: measure the quantities yourself from the drawings, write down your assumptions and exclusions, and price a contingency for the quantity risk you carry.
  • Unit price: make every rate carry its own cost, overhead and margin. A low rate cannot be recovered through quantity.
  • Both: under the current Implementing Regulations, price the quantities exactly as the tender sets them, with no changes or reservations, give prices in figures and in words, and leave no item unpriced unless the tender conditions allow it.
  • Arithmetic: under the current Implementing Regulations, where a unit price and its line total disagree the unit price prevails (except where there is a material error), and the price in words prevails over the price in figures. Corrected errors above 10% of the price list or offer total may lead the examination committee to recommend exclusion.
  • Do not skew rates: under the current Implementing Regulations, the examination committee may re-price items priced without proper study, provided the total offer price does not change; a bidder who refuses is excluded.

See also our guides on preparing the financial offer and arithmetic errors in financial offers.

How do change orders and price adjustment affect either type?

Under the current law, a government entity may issue change orders that increase the contract value by no more than 10% or decrease it by no more than 20%, in accordance with the Regulations. The new law, which takes effect in early January 2027, changes this: change orders may add new items up to 10% of the contract value and increase existing items by up to 20% (with the contractor's consent required beyond a 10% level), the total increase is capped at 20%, and existing items may be decreased by up to 20%. A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it, so check that tender's booklet and announcements.

Price adjustment is narrow in both laws: prices cannot change except for price changes in main items as the Implementing Regulations set, changes in customs duties, fees or taxes, and unforeseen material difficulties. Check the draft contract for how quantity differences found on site are treated; the rules quoted here do not say whether they count toward the change-order limits.

How do you tell which basis a tender uses?

  1. Open the pricing form. A single total line points to a lump sum; rows with quantities and unit rates point to unit pricing. A BOQ may also sit behind a lump sum as a breakdown.
  2. Read the payment terms in the draft contract: fixed instalments or milestones, or payment on measured work.
  3. Look for a measurement clause on how executed work is measured and paid.
  4. Read the variation clause for how added or omitted work is valued.
  5. If the basis is unclear, ask through the platform before the inquiry period closes.

The booklet and the draft contract decide the basis, not the shape of the price table. Read the payment, measurement and variation terms before you price, then price every line exactly as issued.

Frequently asked questions

What is the main difference between a lump sum and a unit price contract?

A lump sum pays one fixed total for a defined scope, so the contractor carries the quantity risk within that scope. A unit price contract pays tender rates on measured quantities, so the entity carries the quantity risk within the BOQ items while the contractor keeps the risk that a rate is wrong.

Can I change a BOQ quantity or rate I think is wrong?

No. Under the current Implementing Regulations the offer is priced as the tender sets its quantities and specifications, with no changes or reservations. Raise it through the platform before the inquiry period closes. Etimad's FAQ says that if the entity changes the BOQ after offers are submitted, those offers are deleted automatically and suppliers are emailed.

What happens if my unit rate and line total disagree?

Under the current Implementing Regulations the unit price prevails (except where there is a material error), and the price in words prevails over figures. The new law, which takes effect in early January 2027, leaves arithmetic rules to its Implementing Regulations, so check the tender booklet.

Can a lump sum price change after award?

Yes, in limited cases. Under the current law a change order may raise the value by up to 10% or lower it by up to 20%. The new law, which takes effect in early January 2027, changes these limits, as described above.

Our team provides pricing analysis for government bids, including cost analysis and market benchmarks. The client owns and approves the final prices.

Related Insights

Explore more practical ideas to improve your bid win rate.

Procurement Glossary

Price Preference for National Products and Local SMEs

Price preference lets local SMEs and national products compete as if rival prices were 10% higher. Here is how it works in Saudi financial evaluation, how to claim it, and a hypothetical example.

Read article →

Procurement Glossary

Advance Payment Guarantee: How Government Advances Work

An advance payment guarantee backs a government advance. The current law caps advances at 10%; the new law, which takes effect in early January 2027, widens what an entity may pay.

Read article →

Procurement Glossary

Tender Cancellation: Grounds, Refunds and Next Steps

Tender cancellation ends a competition before award. Learn the legal grounds, what you recover in fees and guarantees, and what to do next.

Read article →

Need support for your next bid?

Our team helps with bid writing, pricing strategy, and compliance review through final submission.

Book a Consultation