Public competitions closing in 2025 gave bidders a median of 20 calendar days from publication to deadline, and direct purchases 7. See the days by activity and contract size, from NextBid analysis of Etimad award data.


Powered by NextBid Pulse - real-time alerts on Etimad tenders matched to your sectors.Start free →

The tender submission period for public competitions closing in 2025 had a median of 20 calendar days, counted from publication to the bid deadline, and the middle half ran from 16 to 31 days, according to NextBid analysis of Etimad award data. Direct purchases gave a median of 7 days. Weekends and public holidays are counted, so the working time you have is shorter.

The current Implementing Regulations set a floor: 15, 30 or 60 days between announcing a public competition and its bid deadline, depending on estimated cost. The new law, which takes effect in early January 2027, sets no periods itself and leaves them to its new Implementing Regulations. A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it, so check that tender's booklet and announcements.

How many days do tenders give?

It depends on the method. Public competitions and framework agreements gave the same median as in 2024; direct purchases were slightly shorter.

MethodMedian 2025 (days)Middle half 2025 (days)Median 2024 (days)
Public competition2016 to 3120
Direct purchase75 to 148
Framework agreement3118 to 3531

Plan on the median, not the average. The average public competition gave 26.3 days, above the median of 20, because about a third allowed 30 days or more and a few allowed far longer.

How short can the notice get?

Public competitions rarely allow under 15 days (0.02% do). Direct purchases move much faster.

Days allowed, 2025Public competitions (%)Direct purchases (%)
Under 8 days0.051.7
8 to 14 days0.023.3
15 to 29 days65.318.9
30 to 59 days31.13.8
60 days or more3.62.2

Does the time depend on the activity?

Yes, mainly among the longer notices. The median runs from 16 days in trade in new spare parts to 31 in facilities and road operation and maintenance. The table shows the ten activities with the most public competitions closing in 2025, sorted by median.

Activity (public competitions, 2025)Median (days)Middle half (days)
Facilities operation and maintenance3118 to 35
Road operation and maintenance3117 to 34
Information technology2216 to 32
General construction contracting, general works2116 to 32
Security and safety2116 to 32
General building contracting1916 to 31
Trade in tools, machinery and devices1916 to 28
Publishing, printing, advertising and artistic production1816 to 29
Trade in building materials, electrical and sanitary ware1716 to 22
Trade in new spare parts1616 to 24

In eight of the ten activities a quarter of public competitions gave 16 days or fewer (17 and 18 in the other two), so the shortest-notice quarter looks much the same in all ten.

Want these alerts for your sectors? Try NextBid Pulse free →

Do bigger contracts get more time?

Yes. Notice rises steadily with the value of the award.

Award value (awarded public competitions, 2025)Median (days)Middle half (days)
Under SAR 1 million1716 to 22
SAR 1 million to under 5 million1916 to 30
SAR 5 million to under 25 million3331 to 38
SAR 25 million to under 100 million3932.5 to 59.5
SAR 100 million and above6462 to 71

What do the rules say about the period?

  • Current minimums. For a public competition the current Implementing Regulations set 15 days between announcement and the bid deadline for an estimated cost up to SAR 5 million, 30 days above SAR 5 million and below SAR 100 million, and 60 days from SAR 100 million. An entity may shorten them with the Minister's approval. The data fit this pattern but cannot show that the minimum was the reason; check the actual deadline in the tender booklet.
  • The new law. The law, which takes effect in early January 2027, fixes no periods, so its new Implementing Regulations will set them. It also requires the entity to answer inquiries before the receipt period ends, as those Regulations clarify.
  • Extensions and inquiries. Under the current Regulations the receipt period can be extended for justified reasons, such as material errors in the quantities or documents (see how deadline extensions work), and all bidders can see inquiries and answers without the asker's identity. Each booklet sets its question window.
  • Direct purchase. One ground is a low estimated cost: up to SAR 100,000 under the current law and up to SAR 1 million under the new law, with local SMEs first (see direct purchase and limited competition).

What does this mean for your bid?

  • Go or no-go. With a median of 20 days a slow decision is costly, so make the bid or no-bid decision in the first days, after reading the booklet. If you find a tender late, count the days really left, because these figures start on the publication day.
  • Pricing. Supplier and subcontractor quotes depend on other companies replying, so request them at once. Where the median is 16 to 19 days, as in trade, publishing and building contracting, keep price lists current so quotes do not eat the window.
  • Proposal quality. Build your standard workplan to fit 16 days, the most a quarter of public competitions gave in eight of the ten activities. A short window rewards work done before the tender appears: a current company profile, certificates, project sheets and a compliance matrix template. Keep the last days for a final review with our pre-submission checklist.

A public competition closing in 2025 gave a median of 20 calendar days from publication to deadline, and a direct purchase 7. Learn of tenders on publication day and decide go or no-go in the first days.

About the data

  • Source and period. NextBid analysis of Etimad award data for tenders with a bid deadline from 1 January to 31 December 2025, compared with 2024 where stated, with award values as recorded up to 9 October 2026. Each tender counts in its bid deadline year. For the wider picture, see Saudi government tender statistics for 2025.
  • Preparation time. Calendar days from the publication date to the bid deadline, with weekends and public holidays counted. The data hold one deadline per tender, so where an entity extended it, the days include the extension and the original notice may have been shorter.
  • Scope. Every tender with a publication date and a bid deadline in the year, awarded or not. The award value table covers awarded public competitions only: award value is the amount awarded, not the entity's estimated cost, and it can move slightly as more awards are recorded.
  • Middle half and rounding. The middle half lies between the 25th percentile (the days a quarter of tenders fall at or below) and the 75th percentile (the days three quarters fall at or below). Shares are rounded to one decimal, so a set of shares can add up to 99.9 or 100.1.

Frequently asked questions

How many days do you get to submit a bid on Etimad?

It depends on the method. According to NextBid analysis of Etimad award data, public competitions closing in 2025 gave a median of 20 calendar days from publication to the bid deadline (middle half 16 to 31), direct purchases 7 days and framework agreements 31.

What is the minimum tender announcement period in Saudi Arabia?

Under the current Implementing Regulations, a public competition is announced at least 15 days before the bid deadline for an estimated cost up to SAR 5 million, 30 days above that and below SAR 100 million, and 60 days from SAR 100 million. An entity may shorten these with the Minister's approval. The new law, which takes effect in early January 2027, leaves the periods to its new Implementing Regulations.

How long do direct purchases give bidders?

Much less. The median direct purchase closing in 2025 gave 7 days (middle half 5 to 14), and 75.0% gave under 15 days, including 51.7% under 8 days.

Can the bid deadline be extended?

Yes. Under the current Regulations the receipt period is extended for justified reasons, such as material errors in the quantities or tender documents, and the buyers of the documents are notified. The figures here include any extension, because the data hold one deadline per tender.

Every day of that window counts, and it starts on publication day. NextBid Pulse sends email alerts for new tenders from Etimad, Forsah, Tanafos and the National Unified Procurement Company (NUPCO). The free plan covers one sector with a weekly digest, Pulse Pro covers all four sources and adds instant email alerts shortly after a tender is published, and Pulse Intelligence adds reminder emails for the submission, questions-window and guarantee deadlines. Start with the free plan.

Related Insights

Explore more practical ideas to improve your bid win rate.

Market Data

Does the Lowest Price Win Saudi Government Tenders?

The cheapest technically compliant offer won 77.8% of single-winner public competitions with two or more compliant bids closing in 2025. See it by activity, contract size and offers, from NextBid analysis of Etimad award data.

Read article →

Market Data

Single Bid Tenders in Saudi Arabia: 2025 Data

Only 4.8% of awarded Saudi public competitions in 2025 had a single bidder, but 15.4% had one or two. See which activities and contract sizes have the thinnest fields.

Read article →

Market Data

Technical Evaluation Failure Rate in Saudi Tenders (2025)

33.8% of bids in awarded public competitions closing in 2025 failed technical evaluation. See the failure rate by activity, contract size and number of bidders, from NextBid analysis of Etimad award data.