← All Articles

Procurement Glossary

Delay Penalty in Government Contracts: Caps and Waivers

29 November 2026 · 5 min read · By NextBid Bid Experts

A delay penalty is the fine for late performance: up to 6% for supply and 20% for other contracts. The new law, which takes effect in early January 2027, lowers the second cap to 15%.


A delay penalty (غرامة التأخير) is the fine a Saudi government entity charges a contractor that performs late. Under the current Government Tenders and Procurement Law, it may not exceed 6% of the value of a supply contract or 20% of the value of other contracts. The new law, which takes effect in early January 2027, keeps 6% for supply and lowers the cap on other contracts to 15%. The tender booklet (كراسة الشروط والمواصفات) and the contract set the exact rate and how it is calculated, so read them before you price.

What is a delay penalty in a government contract?

It is a fine for missing the completion date or a milestone that the contract fixes. The law sets only the ceiling. The booklet and the contract set the rate, what triggers it and how it is counted, so treat that clause as a cost you carry if the schedule slips.

How high can a delay penalty go?

Under the current law (2019), the caps are those below. The new law, which takes effect in early January 2027, changes the cap on other contracts to 15% and leaves the supply cap where it is.

ItemCurrent lawNew law
Supply contractsUp to 6% of the contract valueUp to 6%
Other contractsUp to 20% of the contract valueUp to 15%
Continuing-service shortfallA fine of up to 20%, plus deduction of the value of work not executedA fine of up to 15%, plus deduction of the value of work not executed
Rate above the capNeeds the Minister's prior approval, disclosed to bidders before they submit offersSame condition

Under the current Implementing Regulations, in general construction, if the delayed part does not compromise the work, the fine may be charged on the delayed works only, capped at 20% of their value. Whether the new Implementing Regulations keep this rule is not yet verified, so check the tender booklet. Which law's cap applies to a contract that comes from a tender offered before the new law takes effect is not yet verified, so check that tender's booklet and announcements.

When is a delay excused?

The current law lists the grounds for extending the contract period and waiving the fine, and the new law, which takes effect in early January 2027, keeps the same grounds and leaves the procedure to its Implementing Regulations. The grounds are:

  • additional works assigned to the contractor;
  • insufficient annual appropriations;
  • delay by the entity, or exigent circumstances;
  • reasons beyond the contractor's control;
  • suspension of the work ordered by the entity.

How do you ask for an extension?

The procedure and any notice period come from the Implementing Regulations and from your contract, so follow the clause your contract contains. As good practice, notify the entity in writing as soon as the cause arises, name the ground that applies, and attach evidence such as dated correspondence, site records and the entity's own instructions.

Delay penalty or deduction: what is the difference?

A delay penalty is a fine for lateness. A deduction removes the value of work that was never executed from what the entity pays. For continuing services the law applies both: a fine for the shortfall and a deduction of the unexecuted work. Under the current law the shortfall fine is capped at 20%. The new law, which takes effect in early January 2027, caps it at 15% and still requires the deduction in every case.

How should you price and plan for delay risk?

Under the current law the cap is 6% for supply and 20% for other contracts. The new law, which takes effect in early January 2027, lowers the cap on other contracts to 15%. The rate, the trigger and the waiver procedure come from the booklet and the contract, so confirm them before you price.

Frequently asked questions

What is the maximum delay penalty in a Saudi government contract?

Under the current law, up to 6% of the value of a supply contract and up to 20% of the value of other contracts. The new law, which takes effect in early January 2027, keeps 6% for supply and lowers the other cap to 15%.

Can an entity set a rate above the cap?

Only with the Minister's prior approval, and bidders must be told before they submit their offers. This condition appears in the current law, and the new law, which takes effect in early January 2027, keeps it.

Can a delay penalty be waived?

Yes, where a listed ground applies, such as additional works, a delay by the entity or reasons beyond the contractor's control. The new law, which takes effect in early January 2027, keeps the same grounds and leaves the procedure to its Implementing Regulations.

Is a delay penalty the same as a deduction for unexecuted work?

No. The penalty is a fine for lateness, while the deduction removes the value of work not executed from the payment. For continuing services the law applies both, and the new law, which takes effect in early January 2027, lowers the fine cap from 20% to 15%.

Delay terms are easiest to handle before you submit, when the clause can still be priced and planned for. Our bid management team supports bids end to end through final submission, with a compliance matrix and pink, red and gold team reviews. Bring us the booklet and we will talk through the bid.

Related Insights

Explore more practical ideas to improve your bid win rate.

Procurement Glossary

Variation Orders in Government Contracts: Saudi Limits

A variation order changes a signed government contract's scope and value. The current law allows +10% and -20%; the new law, which takes effect in early January 2027, changes the limits.

Read article →

Procurement Glossary

Advance Payment Guarantee: How Government Advances Work

An advance payment guarantee backs a government advance. The current law caps advances at 10%; the new law, which takes effect in early January 2027, widens what an entity may pay.

Read article →

Procurement Glossary

Lump Sum vs Unit Price Contracts in Saudi Tenders

A lump sum pays one fixed price for a defined scope; a unit price contract pays tender rates on measured quantities. Here is how each is priced and how to spot which one a booklet uses.

Read article →

Need support for your next bid?

Our team helps with bid writing, pricing strategy, and compliance review through final submission.

Book a Consultation