Variation Orders in Government Contracts: Saudi Limits

25 November 2026 · 6 min read · By NextBid Bid Experts

A variation order changes a signed government contract's scope and value. The current law allows +10% and -20%; the new law, which takes effect in early January 2027, changes the limits.


A variation order (change order, أمر تغيير) is a written instruction from the contracting entity that adds to or reduces the work in a signed government contract, and so changes its value. Under the current Government Tenders and Procurement Law (the 2019 law), the entity may increase the contract value by no more than 10% or decrease it by no more than 20%, in line with the Implementing Regulations. The new law, which takes effect in early January 2027, changes these limits and adds a consent rule for the contractor.

When can the entity issue a variation order?

The current law lets a government entity issue change orders according to its actual needs, within the percentages set out below. The current Implementing Regulations, as amended by Ministry of Finance Decision 1097 (June 2026), add conditions: the additional works must fall within the scope of the contract, the funds must be confirmed first, and the works may be assigned before the entity receives the contracted works or before the contract term ends. The entity also assesses whether the additional works need a longer period.

What are the limits under the current law and the new law?

Under the current law, a change order may increase the contract value by no more than 10% or decrease it by no more than 20%, as the Implementing Regulations provide. The new law, which takes effect in early January 2027, changes this to separate limits for new items and for existing items, summarised below.

VariationCurrent law (in force today)New law (from early January 2027)
Increase through new itemsCovered by the single 10% limit on increasing the contract valueUp to 10% of the contract value, with the contractor's consent
Increase of existing itemsCovered by the same 10% limitUp to 20%, with the contractor's consent required beyond a 10% level
Total increaseNo more than 10% of the contract valueNo more than 20% of the contract value
DecreaseNo more than 20% of the contract valueExisting items up to 20% (more with the contractor's consent)

The new law also allows non-financial terms to change by agreement. Its consent clause does not make plain whether the 10% level is measured on the contract value or on the increase, so confirm the reading in the new Implementing Regulations and the booklet before relying on a figure.

A tender offered before the new law takes effect stays under the current law unless the Minister of Finance decides to apply some of the new rules to it, so check that tender's booklet and announcements. See also what the new law changes.

How is the price of a variation set?

Under the current Implementing Regulations, additional works that have no similar items or quantities in the contract go to the examination committee (لجنة فحص العروض), which reviews the contractor's prices. If the contractor does not accept the committee's outcome, the works are contracted to other bidders under the law and the Regulations. The new law, which takes effect in early January 2027, leaves the procedure to its new Implementing Regulations; whether they keep this committee review is not confirmed, so check the tender booklet.

For items already in the contract, your priced rates are the natural reference point for a change in quantity, so build them to stay workable if quantities move up or down. The booklet and contract set how a changed quantity is paid; a lump sum or unit price contract shapes how much it matters.

How is a variation order different from price adjustment?

A variation order changes the scope or quantities. Price adjustment changes what the same work costs. Under the current law, prices cannot change except for price changes in main items set by the Regulations, changes in customs duties, fees or taxes, and unforeseen material difficulties. The new law, which takes effect in early January 2027, keeps these three cases.

Under the current Implementing Regulations, as rewritten by Ministry of Finance Decision 257 (published in Umm Al-Qura on 25 September 2026), changes in duties, fees and taxes after the bid date are compensated on proof of payment. Other price changes count only if the total contract cost rises by more than 3%; fixed-profit-margin contracts are excluded.

What should a contractor record and check?

  1. Read the variation, payment and guarantee terms in the tender booklet before you price, and send an inquiry in the inquiry window if a term is unclear.
  2. Keep every instruction in writing: its date, the scope added or removed, and the quantities.
  3. Keep a running total of all variations against the original contract value.
  4. Price additional work on the same basis as your original offer (see how to prepare a financial offer).
  5. Raise any effect on time in writing, since the entity assesses whether more time is needed.
  6. Check the consent and notice terms in your contract, and the new law's Implementing Regulations once issued. The new law takes effect in early January 2027.

Under the current law, a change order moves the contract value by up to 10% upward or 20% downward. The new law, which takes effect in early January 2027, changes this to a total increase of up to 20% (new items up to 10%, with the contractor's consent) and decreases of existing items up to 20%, with the contractor's consent also required for an increase of existing items beyond a 10% level.

Frequently asked questions

Can the entity issue a variation order without my agreement?

The current law lets the entity issue change orders according to its actual needs, within the 10% and 20% limits. The new law, which takes effect in early January 2027, requires the contractor's consent for new items and for an increase of existing items beyond a 10% level. Check the consent and notice terms in your contract.

Until when can additional works be assigned?

Under the current Implementing Regulations, additional works may be assigned before the entity receives the contracted works or before the contract term ends. The new law, which takes effect in early January 2027, leaves the procedure to its new Implementing Regulations, so check the booklet and the contract.

Is a variation order the same as a price adjustment?

No. A variation order changes the scope or quantities, while price adjustment deals with price changes in the same work in the cases the law lists. The new law, which takes effect in early January 2027, keeps those cases.

Which law applies to the variation terms of my contract?

A tender offered before the new law, which takes effect in early January 2027, stays under the current law unless the Minister of Finance decides to apply some of the new rules to it. The official texts read for this entry do not say how this applies to variations during performance, so check the booklet.

Our bid management service runs through final submission. If you want to discuss a tender's variation, payment and guarantee terms before you bid, talk to our bid management team.

Related Insights

Explore more practical ideas to improve your bid win rate.

Procurement Glossary

Advance Payment Guarantee: How Government Advances Work

An advance payment guarantee backs a government advance. The current law caps advances at 10%; the new law, which takes effect in early January 2027, widens what an entity may pay.

Read article →

Procurement Glossary

Lump Sum vs Unit Price Contracts in Saudi Tenders

A lump sum pays one fixed price for a defined scope; a unit price contract pays tender rates on measured quantities. Here is how each is priced and how to spot which one a booklet uses.

Read article →

Procurement Glossary

Price Preference for National Products and Local SMEs

Price preference lets local SMEs and national products compete as if rival prices were 10% higher. Here is how it works in Saudi financial evaluation, how to claim it, and a hypothetical example.

Read article →

Need support for your next bid?

Our team helps with bid writing, pricing strategy, and compliance review through final submission.

Book a Consultation